March PTO Presentation

Click below to view the PTO Presentation from March 18, 2026, which shows updated renderings, phasing schedules, design plans, and graphics


Design + Construction Schedule *

•Construction Documents - March 2025 to November 2025
 

•Project Bid - December 2025 through January 2026
 

•Building Construction April 2026 to February 2028

•Move in during February Break 2028​

•Building Completion + Occupancy - February 2028
 

•Demolish Existing Building + Complete Sitework - March to October 2028

*All dates are proposed and subject to change. 

欢迎访问伯灵顿小学建设项目网站。我们鼓励您浏览该网站,以了解有关该项目及其对城镇的影响以及它如何与社区互动的更多信息。

深入了解伯灵顿如何有机会通过 MSBA 合作伙伴关系获得约 36% 的项目成本

Learn how Fox Hill needs to be replaced from both a physical and educational perspective.

Discover how the design of a New Fox Hill school will address the community's needs.

审查项目预算和伯灵顿居民的税收影响。

赞成或反对投票对于福克斯山的未来意味着什么。